HBW's Working Record for Power Industry inTaiwan (Herbert Wang) The 1st contact of power relating facilities was Electro Static Precipitator (ESP) of two sets of 550 MW coal fired boiler in 1990, there were Lurgi’s ESP revamping , turn-key basis, located in HsinTa Thermal Power Station, the winning price was US$ 24,800,000 after competition with ABB, FLS, BABCOCK, NOELL, …etc. the description of project brief: Item Description Key figures Results Remarks 1 Capacity 550Mwe/1,950,000NM3/Hr 550Mwe/1,950,000NM3/Hr 72 Hr test 2. Schedule Unit3 – Aug. 12’93, Unit 4-Feb. 12’93 On schedule 3 Performance Guarantee 35mg/NM3 28mg/NM3 4 Final Acceptance Aug. 12’1993 Aug. 14’1993 5 Budget/cost control US$ 22,000,000 US$ 20,600,000 6 Responsible function Procurement, coordination, local project management, public relation, quality control/assurance, final test & acceptance. Organization chart of project execution: (the names of client were the key to solve the issues and forward the progres